The Haitian state has been spending twice as much to supply Port-au-Prince with electricity since protesters shut down the Péligre hydroelectric plant, the country's largest power facility, in June 2025, Électricité d'Haïti (EDH) production director Markos Fleury told AyiboPost in a report published November 13. Part of the reason is that fuel for thermal plants costs more than the water used by hydroelectric turbines.
Since the sabotage, Port-au-Prince has been supplied by the private company E-Power and the Carrefour thermal plant, which together produce about 30 megawatts, Fleury said. Protesters had damaged five pylons carrying 115,000-volt lines in Mirebalais, in the Centre department, which fed the commune and the capital region.
EDH is seeking 6 million U.S. dollars to restart the plant, according to an assessment submitted to the Ministry of Public Works in March: 3.5 million to repair the pylons and 2.5 million for the plant and the Bas-Plateau network. Fleury said EDH was waiting for the ministry's answer to begin work, provided security improves. Local groups want the state to restore security in Saut-d'Eau and Mirebalais before the plant reopens.
Built by the U.S. Army Corps of Engineers between 1950 and 1956 on the Artibonite River, the Péligre dam produced 54 megawatts with three turbines in June 2019, about 18% of EDH's national output. One of the plant's engineers warned that the longer the shutdown lasts, the greater the risk of damage to equipment and the higher the cost of restarting it.









Comments
No comments yet. Start the conversation.